September 2014

September was a big month, with the guys from Masonry & Lime returning to complete the harling (that will be 950sqm in total!)  But before they arrived there was a lot of prep to do – Mike had to remove the remainder of the cement render and get the downpipes and new vents prepared and Tony was working tirelessly to complete the flushing out coat (with a little help from Paul).

And now for some picture of the top coat going on.  Thanks go to Benny, Trigger, Logan and, of course, Tony.  They even managed to point up one of the windows


Turning to the garden, our fruit trees have had another good year:


And the Glasshouse is settling in nicely:

The summerhouse is approaching completion – just some glazing and the roof to finish:

And here are some more of the gardens:

And last but not least:

Advertisements
This entry was posted in Renovation Diary. Bookmark the permalink.